CourtMassachusetts Appeals Court
DocketAC 25-P-1005
ReleasedAugust 18, 2026
ArguedMay 8, 2026
PanelVuono, Neyman, & Smyth, JJ
Full opinionRead the full text of the decision
A property owner’s consumer-protection demand letter to the City of Chelsea could not satisfy the Massachusetts Tort Claims Act’s presentment requirement because it failed to identify the factual or legal basis of her negligence claim. The Appeals Court affirmed summary judgment for the city on August 18, 2026.
She Ling Wang owns a six-unit residential building in Chelsea. On June 22, 2021, the property flooded with city sewer water, damaging two units. Wang met with city officials the next day and was told to remove the subfloor from the flooded basement, which she did.
Nearly a year later, on May 26, 2022, Wang’s attorney sent the city a letter captioned as a Chapter 93A demand. The letter accused the city of unfair and deceptive conduct: making the damage-resolution process impossible, ignoring construction experts, refusing contact, and failing to reimburse construction expenses. The letter never mentioned flooding, sewer pipes, or negligence.
Wang filed suit two months later asserting six claims. A Superior Court judge dismissed five of them and limited the negligence claim to allegations that the city failed to properly maintain its sewer pipes. The city then moved for summary judgment on the ground that Wang had not properly presented her MTCA claim. A different judge agreed and granted summary judgment. Wang appealed.
The Presentment Requirement
General Laws chapter 258, section 4, bars suit against a public employer unless the claimant first presents the claim in writing to an executive officer within two years of the incident. The statute does not spell out what the presentment must contain. Case law holds that a presentment letter should be precise in identifying the legal basis of a plaintiff’s claim and should not leave educated public officials baffled or misled about the assertion of a claim under chapter 258.
The purpose of presentment is to give the executive officer an opportunity to investigate, settle, and take preventive measures. Courts have said presentment must be made in strict compliance with the statute, though that precept concerns timing and recipient more than content.
What the Court Held
Justice Neyman, writing for a panel that included Justices Vuono and Smyth, held that Wang’s Chapter 93A demand letter was inadequate as a matter of law. The court identified four fatal deficiencies.
First, the letter contained no reference to the factual basis of liability. It said nothing about sewer pipes, the flooding incident, or the city’s alleged failure to maintain infrastructure. Second, the letter identified no legal basis or theory of liability. The word negligence never appeared. The letter did not assert that Wang’s damages were caused by the city’s negligence. Instead, the subject line and body claimed liability under Chapter 93A for conduct occurring after the flood.
Third, the letter made no reference to chapter 258 or the MTCA. While citing the statute is not required, its absence here compounded the other shortcomings. Fourth, the letter gave no date for the incident or injury.
The court held that these combined deficiencies made the letter inadequate to fulfill the statutory purpose of the presentment requirement. The justices were aware of no case where a purported presentment letter failed to reference the cause of action, the factual basis, the legal theory, and the incident date yet still satisfied chapter 258.
The Lulling Exception
Wang argued that the city had waived the presentment requirement by lulling her into believing it was satisfied. The court rejected this argument. The city raised defective presentment as an affirmative defense in its answer, putting Wang on notice. Wang pointed to no evidence supporting her lulling claim. The exception requires that a defendant affirmatively indicate that presentment has been met or waived, and the record contained no such evidence.
Why It Matters
The decision underscores that a demand letter written for one statute cannot automatically serve as presentment under another. A Chapter 93A letter alleging unfair business practices after a flood does not give a city notice of a negligence claim based on defective sewer pipes. Practitioners must ensure that MTCA presentment letters clearly identify the incident, the legal theory, and the factual basis for liability. Generic complaints about government conduct will not suffice.
The ruling also illustrates the limits of substantial compliance. Even though Wang’s letter was timely and went to the right official, its failure to mention the core facts and legal theory doomed her case. The presentment statute is not a mere formality. It serves the concrete purpose of allowing municipalities to investigate and resolve claims before litigation. A letter that leaves officials guessing about what happened and why the city might be liable defeats that purpose.
Wang’s appeal offers no challenge to the earlier ruling that dismissed five of her six claims and narrowed the negligence count to sewer-pipe maintenance. That decision became the lens through which the Appeals Court evaluated her presentment. The mismatch between the demand letter’s focus on post-flood city conduct and the surviving claim’s focus on pre-flood infrastructure maintenance proved fatal.
Read the full opinion: Wang v. City of Chelsea (AC-25-P-1005, August 18, 2026).
