COMMONWEALTH OF MASSACHUSETTS
 PLYMOUTH, ss. SUPERIOR COURT
 CIVIL ACTION
 NO. 13-01214
 CALM GOLF, INC.
 vs.
 RENE J. READ, IN HIS CAPACITY AS TOWN MANAGER OF THE TOWN OF
 DUXBURY, AND ROBERT TROY, ESQ.
 MEMORANDUM OF DECISION AND ORDER ON
 DEFENDANT’S MOTION FOR SUMMARY JUDGMENT
 This action arises out of an award to plaintiff, CALM Golf, Inc.(“Calm”), from the Town
 of Duxbury (represented by its Town Manager, Rene Read) (“Duxbury”), to operate the North
 Hill Country Club and Golf Course (“North Hill”).1 Calm alleges that Duxbury is liable to it for
 breach of contract (Count I), violation of Chapter 93A (Count IV), and violation of the
 Massachusetts Public Bidding Statute, G. L. 30(b) (Count VI).
 Before the Court is Duxbury’s motion for summary judgment. A proper review of the
 record shows that the core facts are largely undisputed. It also shows that this case boils down to
 two simple, controlling propositions. First, did Duxbury’s award to Calm equate to a contract,
 either express or implied? Second, was Duxbury required to conclude a formal contract with
 Calm despite the fact that, as the result of litigation brought by a disappointed bidder – the thenextant
 manager of North Hill, Johnson Golf Management, Inc. (“Johnson) – this Court ordered
 Duxbury not to contract with Calm but rather to continue its contract with Johnson?
1 Count II, alleging misrepresentation against Duxbury, and Counts III and V, all of the counts against defendant
 Robert Troy, were previously dismissed by this Court.
As the answer to both questions is “no,” Duxbury’s motion for summary judgment is
 ALLOWED.
 BACKGROUND
 The following relevant facts are either undisputed or presented in the light most favorable
 to the non-moving party, in accordance with the dictates of Mass. R. Civ. P. 56.
 In September 2008, Duxbury published a Request for Proposal (“RFP”) pursuant to G.L.
 30B for a five-year contract to operate North Hill. Johnson was then the manager of North Hill.
 Calm and Johnson bid for the contract. In December 2008, and for reasons not relevant here,
 Duxbury rejected all bids.
 On December 12, 2008, Johnson sued Duxbury in this Court (Middlesex Superior Court)
 in Johnson Golf v. Town of Duxbury, et al., 08-04641, arising from the bid process (“the
 Johnson Litigation”). On January 8, 2009, the Court in the Johnson Litigation issued a
 temporary restraining order requiring that “Johnson Golf Management Inc., shall continue to
 manage the North Hill Country Club Golf Course until such time as defendant Town of Duxbury
 has awarded a new management contract pursuant to G.L. c. 30B rebidding process that is to
 begin on January 9, 2009 or until further order of the Court.”
 On or about January 9, 2009, Duxbury issued a second RFP for the operation of North
 Hill for five years. Johnson and Calm bid again. Calm’s bid was in excess of $  500,000.
 By memorandum dated January 15, 2009, Duxbury awarded the contract to Calm, writing
 that it “make[s] the Award to Calm Golf, subject to the execution of a contract reflecting the
 terms of the RFP acceptable to the Town.”
 No such contract was ever entered into after this award.
On January 20, 2009, Johnson filed an amended complaint in the Johnson Litigation. On
 January 21, 2009, the Court in that case issued a second temporary restraining order, prohibiting
 Duxbury “from executing a contract with the defendant CALM Golf and from awarding the
 contract to any person or entity other than Johnson Golf.”
 Thereafter, on February 2, 2009, the Court in the Johnson Litigation allowed Johnson’s
 request for injunctive relief, ordering that “Johnson Golf Management, Inc. shall continue to
 manage the North Hill Country Club and Course until such time as [the Johnson Litigation] is
 resolved or until further order of this Court,” and ordering that the then-agreement between
 Duxbury and Johnson “shall remain in place and in force until the resolution of the [Johnson
 Litigation] or until further order of this Court.”
 On or about October 20, 2010, while the Court’s February 2, 2009 order was still in
 force, Calm’s principals met with the Duxbury, at which meeting Duxbury asked, and Calm
 confirmed, that it was ready, willing and able to take over North Hill on a temporary basis in the
 fall of 2010 if needed. No written agreement resulted from this meeting, and Calm did not step
 in to manage North Hill in the fall of 2010 or at any other point.
 On October 25, 2010, the Court in the Johnson Litigation vacated the February 2, 2009
 injunction, but re-instated it on November 24, 2010, writing that “[i]t was not the Court’s
 intention…to permit the town to award the contract to another company during the pendency of
 this action.” The Court again enjoined Duxbury “from executing a contract for operation of the
 North Hill Golf and Country Club until the conclusion of this litigation or further order of this
 Court,” and ordered that Johnson “shall continue to manage” North Hill under the terms of
 Johnson’s contract with Duxbury until the Johnson Litigation was concluded or until further
order of the Court. The Court also noted, however, that its order “does not forbid the Town of
 Duxbury from rebidding the contract.”
 Following the November 24, 2010 order, Duxbury rejected all bids from the January
 2009 bidding process, revoked its award to Calm, and indicated it would re-bid the contract
 under G.L. c. 30B. In March 2011, Duxbury issued a new RFP for North Hill. Neither Calm nor
 Johnson submitted bids; in fact, only one bidder submitted a bid. On March 24, 2011, that
 bidder was awarded the contract.
 On March 30, 2011, the Court in the Johnson Litigation vacated its November 24, 2010
 order.
 Trial was thereafter conducted in the Johnson Litigation. On April 24, 2013, the jury
 found in favor of Johnson that Duxbury had violated G.L. c. 30B by awarding the North Hill
 contract to Calm following the January 2009 RFP process.
 DISCUSSION
 Summary judgment is appropriate when the record shows that “there is no genuine issue
 as to any material fact and that the moving party is entitled to judgment as a matter of law.”
 Mass. R. Civ. P. 56(c); see DuPont v. Commissioner of Corr., 448 Mass. 389, 397 (2007). The
 moving party bears the initial burden of demonstrating that there is no triable issue and that he or
 she is entitled to judgment. Ng Bros. Constr., Inc. v. Cranney, 436 Mass. 638, 644 (2002), citing
 Pederson v. Time, Inc., 404 Mass. 14, 17 (1989); Kourouvacilis v. Gen. Motors Corp., 410 Mass.
 706, 716 (1991). In reviewing a motion for summary judgment, the Court views the evidence in
 the light most favorable to the non-moving party and draws all reasonable inferences in his or her
 favor. Jupin v. Kask, 447 Mass. 141, 143 (2006), citing Coveney v. President & Trs. of the Coll.
of the Holy Cross, 388 Mass. 16 (1983); see also Simplex Techs., Inc. v. Liberty Mut. Ins. Co.,
 429 Mass. 196, 197 (1999).
 As noted above, the first question in this case is whether Duxbury’s award to Calm
 equated to an express or implied contract. On its face, the award was not a contract, and was
 expressly subject to a contract later being negotiated between Duxbury and Calm. See G.L. c.
 30B, §17(a) (“All contracts in the amount of $  10,000 or more shall be in writing”); G.L. c. 259,
 §1 (contracts for performance in excess of one year must be in writing signed by the party to be
 charged); see also, e.g., Mangano v. Town of Wilmington, 51 Mass. App. Ct. 857, 860–61
 (2001) (citations, footnote omitted) (“The request for bids was merely a solicitation for offers.
 No steps were taken by the town which could be interpreted as an acceptance of [the] offer. See
 Dunham v. Boston, 94 Mass. 375, 12 Allen 375, 377, 1866 WL 6376 (1866) (no contract where
 municipal board voted to recommend sale of a parcel of land, vote was approved by the mayor,
 and the city solicitor prepared the deed, but the deed was not signed because alderman objected);
 Edge Moor Bridge Works v. Inhabitants of County of Bristol, 170 Mass. 528, 531–533, 49 N.E.
 918 (1898) (no contract where county commission had invited bids for a project, accepted the bid
 of the plaintiff, notified the plaintiff of the acceptance but then refused to execute a contract for
 construction, because “[t]he vote was but a step in the negotiation … [and] execution of the
 contract was an act to be done in the future”); Al’s Lunch, Inc. v. City of Revere, 324 Mass. 472,
 474–476, 87 N.E.2d 5 (1949) (no contract found where city council voted to authorize the city
 solicitor to take further steps toward sale of real estate, even where vote was communicated to
 plaintiff). Compare Whiting, 370 Mass. at 672, 351 N.E.2d 493 (contract found where
 commissioners voted to approve and accept bid, communicated acceptance to bidder, and
 requested and received balance of bid); Hunt, 25 Mass.App.Ct. at 627, 521 N.E.2d 751 (sellers
accepted bid offer by congratulating highest bidder, returning checks to other bidders, depositing
 check of highest bidder, and signing purchase and sale agreement)”). Nor did the subsequent
 discussions between the parties in October 2010 ripen into a contract.
 There is law that “[w]here the bid solicitor is a governmental entity, numerous cases
 impose liability on an implied contract theory … creat[ing] an implied contract obligating the bid
 solicitor to those conditions” which can result in an award of bid preparation costs for “the
 failure to give fair consideration to a bidder in accordance with the statutory procedure,” New
 England Insulation Co. v. Gen. Dynamics Corp., 26 Mass. App. Ct. 28, 30–32 (1988), or, if bad
 faith is shown, lost profits under certain facts. See, e.g., Peabody Const. Co. v. City of Boston,
 28 Mass. App. Ct. 100, 105–06 (1989) (citations omitted) (“in the absence of bad faith, a bidder
 wrongfully deprived of a contract may recover only his bid preparation costs. However, if a
 bidder has complied with all requirements but is deprived of the contract through some conduct
 of the awarding authority tantamount to bad faith, then the recovery of lost profits is the measure
 of damages”). However, in this case, no rational fact finder could find that there was a contract,
 either express or implied, or that Duxbury acted out of bad faith by failing to conclude a contract
 with Calm. Simply put, it is indisputable that this Court specifically prohibited Duxbury from
 concluding a contract with Calm and specifically ordered Duxbury to continue its contract with
 Johnson. Duxbury thus had no choice but to abandon the January 2009 bid process and start
 anew.
 Accordingly, the first question – was there a contract here – must be answered no. The
 second question posed by this case – was Duxbury required to conclude the contract with Calm
 despite the Court’s order – must also be no. Had Duxbury done so, it would have been in
 violation of this Court’s clear orders and been liable for contempt.
Under these facts, Calm cannot as a matter of law show that Duxbury breached a contract
 (Count I) and also cannot show that Duxbury violated Chapter 93A (Count IV) or violated G. L.
 30(b) (Count VI).
 ORDER
 For the foregoing reasons, Duxbury’s motion for summary judgment on Counts I, IV and
 VI is ALLOWED.
 ______________________________
 MICHAEL D. RICCIUTI
 Justice of the Superior Court
 Dated: December 15, 2017